Installing Cabinet
This section describes a full installation of hardware components in the BYB 501 cabinet. The recommended installation order is from the bottom of the cabinet to the top.
Depending on the configuration, some pieces of hardware can be pre-installed. Therefore, some installation steps may be irrelevant. In that case, ignore the irrelevant step and proceed to the next one.
It is recommended to install the hardware at the cabinet locations described in the instructions below. Although not recommended, it is possible to change the hardware placement in the cabinet. In that case, the following constraints must be regarded:
The batteries must be placed at the lowest position in the cabinet.
The fan unit must always be installed directly above the subracks.
Two subracks must be mounted closely, one above the other.